160x Filetype XLSX File size 0.07 MB Source: www.adb.org
Sheet 1: Assumptions
Outputs Listing | |||||||
Output No. | Description | ||||||
1 | High Voltage Substations | ||||||
2 | High Voltage Transmission Lines | ||||||
3 | Medium and Low Voltage Systems | ||||||
4 | Grid Stabilization | ||||||
5 | Project Management | ||||||
Exchange Rate | 56.25 | Per USD | |||||
Base Cost Estimation Date | 9/30/2013 | ||||||
Inflation Rates | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 |
International | 1.80% | 2.00% | 1.20% | 1.30% | 1.50% | 1.50% | 1.50% |
Domestic | 7.20% | 6.80% | 6.50% | 6.00% | 6.00% | 5.00% | 5.00% |
Source: ERD Website | |||||||
Annual Exchange rate on PPP | 56.25 | 58.9 | 61.98 | 64.86 | 67.74 | 70.08 | 72.5 |
Annual Price Contingency Factors | |||||||
2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | |
Price Contingency - FX Expenditure | 0.45% | 1.45% | 3.07% | 4.36% | 5.82% | 7.41% | 9.02% |
Price Contingency - LC Expenditure | 1.80% | 5.26% | 12.26% | 19.26% | 26.42% | 33.35% | 40.02% |
Annual exchange rate adjustment factor | 0.0000% | -0.0800% | -0.1644% | -0.2360% | -0.3015% | -0.3508% | -0.3985% |
Physical Contingency Matrix | Rate | ||||||
001 | Land Acquisition | 5.00% | |||||
002 | Environmental and Resettlement | 5.00% | |||||
003 | HV Transmission Equipment | 10.00% | |||||
004 | HV Transmission Erection | 10.00% | |||||
005 | HV Substation Erection | 5.00% | |||||
006 | HV Substation Equipment | 5.00% | |||||
007 | ML Substation Equipment | 5.00% | |||||
008 | ML Substation Erection | 5.00% | |||||
009 | Grid Stabilization Equipment | 10.00% | |||||
010 | Grid Stabilization Erection | 10.00% | |||||
011 | Project Management | 5.00% | |||||
012 | Consulting Services | 5.00% | |||||
Taxes on base cost of Works and Goods | |||||||
Excise Duty | 10.30% | ||||||
Central Sales Tax (Base+Excise) | 2.00% | ||||||
Total Taxes | 12.51% | ||||||
Taxes on base cost of consulting services | |||||||
Service Tax | 10.20% | ||||||
Associated Civil Works | 10.00% | ||||||
Freight & Insurance (Base + Civil) | 5.00% | ||||||
The FX component in each package is to be updated in Column H of the Consolidated Investment Plan page |
Cat Code | Package No. | Package | Ex-works Cost | Associated Civil Works | Excise Duty | Sales Tax | Service Tax | Freight and Insurance | Total Cost |
004 | HVTR1 | Towers Material 400 kV D/C Twin Moose Conductors | 551.07 | 56.76 | 12.16 | 27.55 | 647.54 | ||
004 | HVTR2 | Towers Erection 400 kV D/C Twin Moose Conductors | 180.19 | 180.19 | |||||
004 | HVTR3 | Towers Material 400 kV LILO Jaisalmer - Jodhpur-Merta | 527.24 | 54.31 | 11.63 | 26.36 | 619.54 | ||
012 | C01 | Grid Stabilization Design and Implementation consultant | 35.72 | 3.64 | 39.36 | ||||
012 | C02 | Project Management Consultant | 126.56 | 12.91 | 139.47 | ||||
004 | HVTR4 | Towers Erection 400 kV LILO Jaisalmer - Jodhpur-Merta | 199.24 | 199.24 | |||||
004 | HVTR5 | Towers Material 400 kV Twin D/C Ramgarh - Akal | 320.09 | 32.97 | 7.06 | 16 | 376.12 | ||
004 | HVTR6 | Towers Erection 400 kV Twin D/C Ramgarh - Akal | 151.84 | 151.84 | |||||
003 | HVTR7 | Conductor Package | 1,742.40 | 1,742.40 | |||||
009 | GS1 | Static VAR Compensators | 375.00 | 38.63 | 8.27 | 18.75 | 440.65 | ||
009 | GS2 | Communications Equipment | 400.00 | 41.2 | 8.82 | 20 | 470.02 | ||
009 | GS3 | Software | 500.00 | 51.5 | 11.03 | 25 | 587.53 | ||
009 | GS4 | Computers and Hardware | 70.00 | 7.21 | 1.54 | 3.5 | 82.25 | ||
010 | GS5 | Civil works | 50.00 | 5.15 | 1.1 | 2.5 | 58.75 | ||
005 | HVSS1 | Akal Substation 400 kV | 265.65 | 26.57 | 27.36 | 5.86 | 14.61 | 340.05 | |
005 | HVSS2 | Bhadla 400x220 2x315 MVA Substation | 570.57 | 57.06 | 58.77 | 12.59 | 31.38 | 730.37 | |
005 | HVSS3 | Bikaner 400 kV Substation Augmentation | 138.13 | 13.81 | 14.23 | 3.05 | 7.6 | 176.82 | |
006 | HVSS4 | Transformers | 480.12 | 49.45 | 10.59 | 24.01 | 564.17 | ||
006 | HVSS5 | Shunt Reactors | 404.52 | 41.67 | 8.92 | 20.23 | 475.34 | ||
007 | MLSS1 | Ramgarh 220/132 kV Substation | 624.63 | 62.46 | 34.35 | 721.44 | |||
007 | MLSS2 | Bhadla 220/132 kV Substation | 740.03 | 74.00 | 40.7 | 854.73 | |||
008 | MLSS3 | Ramgarh 220/132 kV, 132/33 kV Substation Equipment | 306.62 | 30.66 | 16.86 | 354.14 | |||
008 | MLSS4 | Kanasar 220/132 kV, 132/33 kV Substation Equipment | 305.72 | 30.57 | 16.81 | 353.10 | |||
007 | MLSS5 | Kanasar Extension of 1 220 kV feeder bay | 5.90 | 0.59 | 0.32 | 6.81 | |||
Total Procurements | 9,071.24 | 295.72 | 479.21 | 102.62 | 16.55 | 346.53 | 10,311.87 |
Cat Code | Pkg No. | Package | Base Cost (incl. CW) | Taxes | F&I | Total | FX % | FX Amt | LC Amt |
001 | LROW | Land Acquisition and Right of Way | 35.45 | 35.45 | - | 35.45 | |||
002 | RENV | Resettlement and Environment | 14.76 | 14.76 | - | 14.76 | |||
003 | HVTR7 | Conductor Package | 1,742.40 | - | - | 1,742.40 | - | 1,742.40 | |
004 | HVTR1 | Towers Material 400 kV D/C Twin Moose Conductors | 551.07 | 68.92 | 27.55 | 647.54 | 30.00% | 194.26 | 453.28 |
004 | HVTR2 | Towers Erection 400 kV D/C Twin Moose Conductors | 180.19 | - | - | 180.19 | - | 180.19 | |
004 | HVTR3 | Towers Material 400 kV LILO Jaisalmer - Jodhpur-Merta | 527.24 | 65.94 | 26.36 | 619.54 | 30.00% | 185.86 | 433.68 |
004 | HVTR4 | Towers Erection 400 kV LILO Jaisalmer - Jodhpur-Merta | 199.24 | - | - | 199.24 | - | 199.24 | |
004 | HVTR5 | Towers Material 400 kV Twin D/C Ramgarh - Akal | 320.09 | 40.03 | 16.00 | 376.12 | 30.00% | 112.84 | 263.28 |
004 | HVTR6 | Towers Erection 400 kV Twin D/C Ramgarh - Akal | 151.84 | - | - | 151.84 | 50.00% | 75.92 | 75.92 |
005 | HVSS1 | Akal Substation 400 kV | 292.22 | 33.22 | 14.61 | 340.05 | - | 340.05 | |
005 | HVSS2 | Bhadla 400x220 2x315 MVA Substation | 627.63 | 71.36 | 31.38 | 730.37 | 25.00% | 182.59 | 547.78 |
005 | HVSS3 | Bikaner 400 kV Substation Augmentation | 151.94 | 17.28 | 7.60 | 176.82 | 25.00% | 44.21 | 132.62 |
006 | HVSS4 | Transformers | 480.12 | 60.04 | 24.01 | 564.17 | 80.00% | 451.34 | 112.83 |
006 | HVSS5 | Shunt Reactors | 404.52 | 50.59 | 20.23 | 475.34 | 80.00% | 380.27 | 95.07 |
007 | MLSS1 | Ramgarh 220/132 kV Substation | 687.09 | - | 34.35 | 721.44 | - | 721.44 | |
007 | MLSS2 | Bhadla 220/132 kV Substation | 814.03 | - | 40.70 | 854.73 | - | 854.73 | |
007 | MLSS5 | Kanasar Extension of 1 220 kV feeder bay | 6.49 | - | 0.32 | 6.81 | - | 6.81 | |
008 | MLSS3 | Ramgarh 220/132 kV, 132/33 kV Substation Equipment | 337.28 | - | 16.86 | 354.14 | - | 354.14 | |
008 | MLSS4 | Kanasar 220/132 kV, 132/33 kV Substation Equipment | 336.29 | - | 16.81 | 353.10 | - | 353.10 | |
009 | GS1 | Static VAR Compensators | 375.00 | 46.90 | 18.75 | 440.65 | 100.00% | 440.65 | - |
009 | GS2 | Communications Equipment | 400.00 | 50.02 | 20.00 | 470.02 | 100.00% | 470.02 | - |
009 | GS3 | Software | 500.00 | 62.53 | 25.00 | 587.53 | 587.53 | - | |
009 | GS4 | Computers and Hardware | 70.00 | 8.75 | 3.50 | 82.25 | 100.00% | 82.25 | - |
010 | GS5 | Civil works | 50.00 | 6.25 | 2.50 | 58.75 | 100.00% | 58.75 | - |
011 | PM | Project Management | 687.53 | 687.53 | 100.00% | 687.53 | - | ||
012 | C01 | Grid Stabilization Design and Implementation consultant | 35.72 | 3.64 | - | 39.36 | 40.00% | 15.74 | 23.62 |
012 | C02 | Project Management Consultant | 126.56 | 12.91 | - | 139.47 | 30.00% | 41.84 | 97.63 |
Grand Total | 10,104.70 | 598.38 | 346.53 | 11,049.61 | 4,011.60 | 7,038.02 |
no reviews yet
Please Login to review.