sheet 1 cover fiber construction gantt diagram lt release date gt sheet 2 aerial gantt chart for fiber construction template wbs task name start date end date start on day ...

icon picture XLSX Filetype Excel XLSX | Posted on 14 Aug 2022 | 3 years ago
Partial file snippet.
Sheet 1: Cover














Fiber Construction Gantt Diagram







































<Release Date>



































Sheet 2: Aerial

GANTT CHART FOR FIBER CONSTRUCTION TEMPLATE














































































































WBS
TASK NAME START DATE END DATE START ON DAY* DURATION* (WORK DAYS) TEAM MEMBER PERCENT COMPLETE
1 Permit Acquisition






1.1
Produce Documentation for permit requests 1/5/2020 1/15/2020 0 10 Vendor#1 100%
1.2
Right of Ways and Property Permits 1/15/2020 2/14/2020 10 30 Vendor#1 60%
1.3
Administrative Construction Licensing 2/14/2020 3/15/2020 40 30 Vendor#1 40%
2 Path Survey & Terrain Analysis






2.1
Technical Survey (preparation and generation of report) 3/15/2020 3/25/2020 70 10 Vendor#1 100%
2.2
Engineering and Structural Evaluation 3/25/2020 4/4/2020 80 10 Vendor#1 80%
3 Construction






3.1
Soil excavation and ground cleaning 4/4/2020 4/14/2020 90 10 Vendor#1 100%
3.2
Pole storage and inspection 4/14/2020 4/19/2020 100 5 Vendor#1 60%
3.3
Pole hole digging 4/19/2020 4/24/2020 105 5 Vendor#1 40%
3.4
Pole planting 4/24/2020 4/29/2020 110 5 Vendor#1 20%
3.5
Concrete Casting 4/29/2020 5/9/2020 115 10 Vendor#1 100%
3.6
Pole stays 5/9/2020 5/14/2020 125 5 Vendor#1 100%
3.7
Cable pole supports 5/14/2020 5/19/2020 130 5 Vendor#1 100%
3.8
Pole labeling 5/19/2020 5/23/2020 135 4 Vendor#1 100%
4 Fiber Cable Installation and Commissioning






4.1
Fiber drum storage and inspection 5/23/2020 5/25/2020 139 2 Vendor#1 100%
4.2
Installation and verification of ADSS terminations and supports 5/25/2020 5/30/2020 141 5 Vendor#1 80%
4.3
ADSS leveling 5/30/2020 6/9/2020 146 10 Vendor#1 60%
4.4
Cable tensioning 6/9/2020 6/19/2020 156 10
100%
4.5
Commissioning 6/19/2020 6/24/2020 166 5 Vendor#1 100%
5 In-building access






5.1
In building access point construction 6/24/2020 6/29/2020 171 5
100%
5.2
In building cable routing 6/29/2020 7/1/2020 176 2
100%
5.3
ODF termination 7/1/2020 7/2/2020 178 1 Vendor#1 100%








































































































































The words contained in this file might help you see if this file matches what you are looking for:

...Sheet cover fiber construction gantt diagram lt release date gt aerial chart for template wbs task name start end on day duration work days team member percent complete permit acquisition produce documentation requests vendor right of ways and property permits administrative licensing path survey amp terrain analysis technical preparation generation report engineering structural evaluation soil excavation ground cleaning pole storage inspection hole digging planting concrete casting stays cable supports labeling installation commissioning drum verification adss terminations leveling tensioning inbuilding access in building point routing odf termination...

no reviews yet
Please Login to review.