   MDOT Fee Analysis - Prior to 2020 MAP
      Sponsor Fee Analysis - Post 2020 
      MAP
      Sponsor must perform a price or cost analysis for every 
      Architectural/Engineering contract.
       Contracts less than $100,000 - Comparative analysis can be 
        done with similar projects or a detailed fee analysis
       Contracts anticipated to be greater than $100,000 - A 
        detailed fee/cost analysis is required.
     Contracts under $100,000
      Comparative analysis of similar work at your airport
      Comparative analysis of similar work at another airport 
          Contracts over $100,000
          Preparation of an Independent Fee Estimate (IFE) can be completed by:
          1.   A sponsor having staff with experience in estimating the professional 
               services.
          2.An independent engineering, architecture, or planning consultant retained 
           to prepare an IFE, provided this consultant was not on the pre-selection 
           short-list. 
           IFE is required prior to receiving the consultant’s proposal to properly 
             evaluate the cost of professional services.
           The IFE is intended to be used as a negotiation tool by the sponsor.
           The IFE must address direct labor work hours, labor rates, general and 
             administrative overhead, non-salary expenses and a reasonable profit. 
           A IFE is an AIP eligible and reimbursable cost. Sponsors must present IFE 
             reimbursement requests to their AERO Project Manager at same time we 
             fund the project or phase.  
    Negotiations
    After developing a detailed scope of services, and after the IFE 
    requirements have been satisfied, the sponsor may enter into 
    negotiations with the consultant.
    A general review standard used within the FAA/industry is 
    whether the total fee proposal, as well as individual tasks within 
    the proposal, is within 10% of the IFE. When differences exceed 
    10%, the sponsor and IFE preparer should review those areas 
    with the consultant to determine if there is a misunderstanding of 
    the scope of services or level of effort required to complete the 
    work. 
The words contained in this file might help you see if this file matches what you are looking for:

...Mdot fee analysis prior to map sponsor post must perform a price or cost for every architectural engineering contract contracts less than comparative can be done with similar projects detailed anticipated greater is required under of work at your airport another over preparation an independent estimate ife completed by having staff experience in estimating the professional services architecture planning consultant retained prepare provided this was not on pre selection short list receiving s proposal properly evaluate intended used as negotiation tool address direct labor hours rates general and administrative overhead non salary expenses reasonable profit aip eligible reimbursable sponsors present reimbursement requests their aero project manager same time we fund phase negotiations after developing scope requirements have been satisfied may enter into review standard within faa industry whether total well individual tasks when differences exceed preparer should those areas determine ...

no reviews yet
Please Login to review.